Atturra launches Powerlink network incident system
Thu, 17th Sep 2026
Atturra has implemented a new Network Incident Management System at Powerlink Queensland as part of Powerlink's Next Generation Network Operations program.
The project replaces legacy systems and databases that had been in place for two decades. It brings incident, hazard and risk information into a single environment and integrates with Powerlink's SAP asset management platform.
Powerlink operates a high-voltage electricity transmission network that supplies more than five million Queenslanders and 241,000 businesses. Its infrastructure stretches 1,700 kilometres from Cairns to New South Wales and includes 15,449 circuit kilometres of transmission lines and 152 substations.
The new system was built on SafetySuite for SAP and extended with custom SAP applications. It also uses SAP Fiori Launchpad, SAP BTP, OData services and Esri ArcGIS integration to support network incident, risk and hazard management for field and control room staff.
According to the companies, the system gives users real-time visibility across operational information and streamlines communication around incident management activities. The design includes a Smart Search tool, an unplanned outage application for root-cause traceability, automated notification workflows, and spatial data mapping through ArcGIS.
For Powerlink, the change marks a shift from older operational tools to a more centralised approach to safety and risk management. The system is intended to improve visibility, traceability and decision-making across network operations.
The implementation sits within Powerlink's broader Next Generation Network Operations program, which focuses on updating core operational systems. Atturra designed and built a hybrid model with Powerlink and has now commissioned the system.
Operational shift
The work also reflects increasing pressure on electricity network operators to improve oversight of asset risks and incident responses as grids become more complex. Transmission businesses face demands to maintain reliability while adapting their networks to changing generation sources and operating conditions.
Atturra said the project was among the largest and most technically complex it has delivered. Under an ongoing arrangement, the company will continue to support and enhance the system until 2030 and beyond.
The system has now been commissioned and will remain under Atturra's support and enhancement management for the rest of the decade and beyond.